Markets. Drainage/Bank Protection.

Pantano Wash Permanent Bank Stabilization (Speedway Blvd. to Tanque Verde Road)
Tucson, AZ

Project Info
2010
$2.9 M
84% Self-performed
Installation of soil cement bank protection along a segment of the Pantano Wash between Speedway Boulevard and Tanque Verde Road. Overall project included approximately 2,750 linear feet on the east bank and 3,670 linear feet on the west bank. Also included a 12' paved maintenance path on both banks, barricade railing, and two soil cement grade control structures.