CMC Steel Arizona – Baghouse Installation
Mesa, AZ
Project Info
2008/09
$5.4 M
96%
Self-performed
Fabricate and erect a 30' x 67' x 117' Core Ten Steel baghouse with penthouse on top that contained two chain operated hoists to change out the 2400 bags contained in 20 chambers within the baghouse. A Cyclone was fabricated on site and erected into the ducting in front of the baghouse and a conveyor system installed to transfer dust out to a separate silo. Quench and Lime Towers were erected and all systems were connected by 12' diameter ducting that was supported and accessed by a stair tower 110' tall. The entire project contained over 3,061,000 pounds of steel.