Markets.
Earthwork.
Clearwater Renewable Resource Facility
Tucson, AZ
Project Info
2002/03
$11.7 M
95%
Self-performed
Construction of eleven recharge basins (2 million cubic yards of excavation), two miles of 54 inch mainline HDPE pipe with 42 inch HDPE laterals to each basin. 42in., 30in., 24in. and 20in. steel inlet pipe and valves, concrete distribution structures at each basin and the electrical and instrumentation for the system.